Work is progressing nicely on this block of three houses in Dulwich. The first fix mechanical and electrical work has been completed and the dryliners have started on site. The picture below is a good picture of the front elevation of the building. The slate roof is complete. We used a ventilated dry ridge system. The timber sash windows have begun to be installed as well on site so in general the contract is on programme and will hit the the targeted completion date.