Chiswick Basement Contract Progress

Posted · Add Comment



Work is progressing well on our basement contract which is being carried out in Chiswick. We have formed a lightwell at the front of the property which has enabled us to drop our 1.6 ton excavator into the basement to carry out the dig and also to allow us to put in place the conveyor to take the spoil out. We are underpinning to a depth of 3m. We are currently half way through the underpinning phase which also entailed the erection of supporting steel beams to the underside of the ground floor as the works proceeded. There is good progress on site to date.