Chiswick – Piling on the banks of the Thames River

Posted · Add Comment

We have started the construction on this residential contract. Prior to Christmas we demolished the existing building. We encountered some deep concrete from the existing structure which took an extra couple of days but we got over that and are now in to the building phase of the contract. We have started piling with 300mm diameter piles ranging in depth from 7m-10m. Site access is restricted in that we have to come in through an underpass 2.8m wide and 2.7m high so your typically London contract. We anticipate to complete the piling works this week and then form the ground beams and slab. We will be ready for brickwork in February.

Piling Chiswick