Raft Foundation Twickenham

Posted · Add Comment
Works commenced on this raft foundation and associated drainage on Saturday 21st July and was completed on Thursday 26th July. The site was initially stripped of topsoil and reduced dig carried out. Type 2 hardcore was put in place and the shutters were put in place for the raft. The raft reinforced with 200mm thicj of concrtee and approx. 800mm deep on the perimeter. 4 pockets were formed in the slab in order that the client could fix in place steel posts for the raised swimming pool. We carried out associated drainage works as you can see from the two white gullies in the picture which will take the run off from the pool.